Vehicles move past electricity pylons in Gurugram, India, September 11, 2025. REUTERS/Bhawika Chhabra
C
CNBC TV1810-02-2026, 19:08

India's Solar Boom Outpaces Grid: Rajasthan Faces 4 GW Curtailment Crisis

  • India's rapid solar plant construction has outpaced grid capacity, leading to severe curtailment in renewable-dense states.
  • Rajasthan is experiencing a major crisis with over 4 GW of commissioned solar capacity facing near-complete curtailment during peak hours.
  • The issue stems from a governance failure in managing the interface between generation, transmission readiness, and grid operations.
  • Projects operating under Temporary General Network Access (T-GNA) are disproportionately affected, with near-zero injection during peak solar times.
  • Policymakers need to implement immediate correctives like proportionate curtailment, temporary reallocation of GNA margins, and clearer transmission unlock timelines to prevent a national crisis.