40 दिन के कम समय में ट्रैक का काम पूरा करने का डिवीजन ने बनाया रिकार्ड.
Railways
N
News1806-01-2026, 07:22

Jhansi Station Sets Record: Ballastless Track Built in 40 Days, Boosts Safety & Efficiency

  • Indian Railways' Jhansi Station completed a 672-meter ballastless track on Platform No. 3 in a record 40 days, becoming a role model.
  • The project, started on November 25, replaced old washable apron with modern ballastless technology for durability and cleanliness.
  • Ballastless tracks minimize maintenance, prevent waterlogging, enhance passenger safety, and improve train operations for 35 years.
  • Work involved removing 1400 cubic meters of debris, pouring 700 cubic meters of M-40 grade concrete, and fitting 1120 sleepers.
  • Led by DRM Anirudh Kumar, this achievement in Jhansi Division will guide similar rapid infrastructure upgrades across other stations.

Why It Matters: Jhansi Station's record 40-day ballastless track completion sets a new standard for railway infrastructure.