Kirari Waterlogging: Delhi Govt Blames Past Negligence, Promises 2026 Completion

  • Delhi government's 'Claims vs. Reality' report blames 11 years of previous AAP government for Kirari's severe waterlogging.
  • Only 43 lakh rupees were spent on sewerage maintenance in Kirari over the past 11 years, deemed negligible for the area.
  • A sewer project approved in December 2020, meant for completion by December 2024, was stalled due to administrative failures.
  • Audit revealed Kirari generates 36 MGD sewage, but only a 15 MGD treatment plant is operational, showing poor planning.
  • Current government claims sewer laying work is now 84% complete (340 km) and aims for full completion by June 2026, with new flood control projects underway.

Why It Matters: Delhi government highlights past negligence in Kirari's waterlogging issue, promising resolution by June 2026.