NFR Boosts Electrification: Araria-Thakurganj Section Gets 132 kV Line

National
N
News18•20-12-2025, 09:56
NFR Boosts Electrification: Araria-Thakurganj Section Gets 132 kV Line
- •Northeast Frontier Railway commissioned a 132 kV transmission line in the Araria-Thakurganj section.
- •The 5.9 km overhead line from Araria GSS to Araria TSS was commissioned on December 17, 2025.
- •This infrastructure enhances power availability, operational reliability, and capacity for electric trains in North Bihar.
- •PCEE inspected and commissioned the Araria and Araria Court–Bibiganj section (67.186 RKM) on October 30, 2025.
- •The project aligns with Indian Railways' net-zero carbon emissions goal by 2030, promising faster, more efficient trains.
Why It Matters: NFR's new 132 kV line significantly strengthens electrification, boosting efficiency and sustainability in North Bihar.
✦