Hinjawadi Metro Faces New Delays; PMRDA Considers Partial Launch Amid Unfinished Stations

Pune
N
News18•27-12-2025, 12:41
Hinjawadi Metro Faces New Delays; PMRDA Considers Partial Launch Amid Unfinished Stations
- •Pune Metro Line 3 (Hinjawadi-Shivajinagar) faces further delays, missing the December 2025 deadline set by CM Fadnavis.
- •Approximately 9% of the project work remains incomplete, with 11 out of 23 stations lacking basic facilities like escalators and parking.
- •Despite delays, the main corridor, tracks, and two metro train sets are ready, with successful speed tests conducted.
- •PMRDA is now considering starting metro services by excluding the incomplete stations to meet public demand.
- •The project, costing ₹8312 crore, has a new deadline of March 31, 2026, extended by 543 days due to land acquisition and permit issues.
Why It Matters: Hinjawadi Metro faces delays but may partially launch, leaving citizens dissatisfied with extensions.
✦