Transmission woes curtail 4.3 GW Rajasthan solar, Rs 20,000 Cr projects at risk.

  • Nearly 4,300 MW of solar capacity in Rajasthan faces complete daytime curtailment due to inadequate transmission infrastructure.
  • This affects 26 solar projects, including those by Adani, ReNew, and ACME, putting approximately Rs 20,000 crore at risk.
  • Projects operating under temporary general network access (T-GNA) are curtailed as long-term GNA exhausted available transmission margins.
  • The commissioning of the 765 kV Khetri-Narela line added only 600 MW capacity, while 4,375 MW was operationalized under long-term GNA.
  • Industry sources urge the government for short-term relief, including a Special Protection Scheme and dynamic reallocation of unused GNA margins.

Why It Matters: Transmission constraints threaten Rajasthan's solar projects, risking India's green energy goals.