News1825-12-2025, 22:04

BMC Halts Bullet Train Excavation at BKC Over Pollution Rule Violations

  • BMC issued a stop-work notice for excavation at the BKC bullet train site due to violations of pollution mitigation rules, specifically GRAP 4 guidelines.
  • The action follows a reprimand from the Bombay High Court to BMC for not seriously addressing pollution control.
  • Civic officials found a lack of essential dust-control measures like misting machines, water sprinklers, and anti-smog towers at the site.
  • NHSRCL claims 85% excavation is complete and largely compliant, but BMC demands immediate rectification of lapses.
  • The halt only affects excavation work; other construction activities continue, but it may impact the overall project timeline.

Why It Matters: BMC stops BKC bullet train excavation due to pollution rule breaches, impacting project timeline.