NH-66 Kerala: Aug 2026 Completion Set, But Delays & Safety Woes Persist

India
N
News18•11-12-2025, 22:18
NH-66 Kerala: Aug 2026 Completion Set, But Delays & Safety Woes Persist
- •National Highway-66 in Kerala is now expected to be completed by August 2026, with Rs 16,500 crore spent so far.
- •Project delays are attributed to additional works, material shortages, financial constraints, and extended monsoon periods.
- •Five sections, totaling 172 km, have achieved over 80% progress, with most revised completion deadlines set for March-June 2026.
- •MoRTH acknowledged drainage failures and waterlogging in Kannur due to construction, requiring new cross-drainage structures.
- •An RS wall collapse in Kollam, caused by weak foundation soil, led to NHAI suspending the involved concessionaire and independent engineer from future bidding.
Why It Matters: NH-66 delays and quality issues impact Kerala's infrastructure and public safety.
✦