Minor Contractor Stalls Delhi-Mumbai Expressway's Rs 1 Lakh Cr Project

  • NHAI issues termination notice to Roadway Solutions India Infra Limited (RSIIL) for slow progress on Delhi-Mumbai Expressway's Jujuwa-Gandeva section in Gujarat.
  • Only 4.5% work completed in 16 months against an expected 70% for the 35 km stretch, despite an 18-month contract.
  • RSIIL failed to deploy necessary machinery and complete utility shifting, leading to significant project delays.
  • The contractor's previous contract for the same sections was cancelled in March 2023, but they re-secured it in November 2023.
  • RSIIL blames land unavailability for delays, while NHAI demands a satisfactory response within 15 days to avoid contract termination.

Why It Matters: A contractor's repeated delays threaten the timely completion of the ambitious Delhi-Mumbai Expressway.