Mumbai Civic Body Faces ₹55 Crore Claim Over Stalled Robotic Parking Project

N
News18•06-02-2026, 10:04
Mumbai Civic Body Faces ₹55 Crore Claim Over Stalled Robotic Parking Project
- •A parking contractor has demanded ₹55 crore compensation from the Mumbai Municipal Corporation for a stalled robotic parking tower project.
- •The ₹122 crore project, designed to ease traffic in South Mumbai and aid Mumbadevi temple visitors, was nearing completion.
- •Assembly Speaker Rahul Narvekar stayed the project in July 2024, citing local complaints and the temple's heritage status.
- •M/s SMS Limited, the contractor, claims the work stoppage is due to political pressure and seeks compensation for financial losses.
- •Municipal Commissioner Bhushan Gagrani had warned of increased costs due to delays and has written to the state government twice, awaiting a response.
✦