HAL’s gas turbine engine project hit by delayed test-bed approvals, says Parliament panel
Business
M
Moneycontrol12-12-2025, 12:58

Test-Bed Approval Delays Stall HAL's Gas Turbine Engine Project: Panel

  • HAL's gas turbine engine project faces significant delays due to slow test-bed approvals and procurement bottlenecks, as highlighted by a Parliament panel.
  • The Committee on Public Undertakings (CPU) urged the Ministry of Defence (MoD) to provide a definitive action plan with timelines and funding for critical testing infrastructure.
  • Delays, including land clearance issues, have added over three years to the project, leading HAL to write off Rs 159.23 crore.
  • The project involves developing a 25 kN engine for jet trainers and a turboshaft engine for helicopters, with Stage II ongoing since 2018.
  • The CPU warned that continued delays undermine India's "Atmanirbhar Bharat" goals in strategic aerospace systems.

Why It Matters: Bureaucratic delays hinder India's critical defense self-reliance goals.