Parliament Panel Flags Delays, Urges Faster Green Clearances for Coal Mines

  • Parliamentary panel flags significant delays in environment and forest clearances for coal mining projects.
  • Panel recommends streamlining procedures, strengthening digital systems, and improving inter-agency coordination.
  • Forest clearances can take up to 34 months, with private operators facing longer delays than public sector undertakings.
  • Key approvals from DGMS and CGWA are not integrated into digital systems, causing duplication and execution delays.
  • Concerns were raised over the low number of state-level environmental clearances granted for projects under 500 hectares.

Why It Matters: Slow environmental approvals for coal mines threaten India's energy security and economy.