After a decade in limbo, Jaypee homebuyers finally see possession on the horizon
Business
M
Moneycontrol13-01-2026, 08:54

Jaypee Homes: 6,000 Units Near Delivery After Insolvency, Buyers Cautiously Optimistic

  • Suraksha Group, after taking over debt-laden Jaypee Infratech Ltd (JIL) in 2024, has completed construction of 5,989 residential units in Noida.
  • Occupancy Certificates (OCs) have been secured for 3,135 units across 31 towers, allowing possession and registrations to begin.
  • Another 2,854 units across 32 towers are awaiting regulatory approvals, with OCs expected in the coming months.
  • This marks a significant turning point for thousands of homebuyers who have been paying EMIs for over a decade without possession.
  • Buyers express cautious optimism, emphasizing the need for timely handover, completion of common facilities, and basic services.

Why It Matters: Thousands of Jaypee homebuyers in Noida are finally seeing progress with nearly 6,000 units nearing delivery.