Kanpur DM Orders Manpower Boost for CM-GRID Road Projects Amid Slow Pace

  • Kanpur DM Jitendra Pratap Singh expressed displeasure over the slow progress of CM-GRID road projects during an inspection at Nagar Titli Chauraha.
  • The DM instructed the Municipal Corporation to take action against the construction agency for insufficient manpower and accelerate work.
  • Separate teams for HDP, FC, and finishing tasks were ordered to be deployed to speed up construction at multiple locations.
  • Kanpur has 13 CM-GRID projects across three phases; Phase one (5 projects, 16.66 km, ₹150 crore) started in June 2025 and is due for completion by November 2026.
  • DM emphasized strict adherence to DPR, daily monitoring, and phased work to minimize public inconvenience and ensure timely, quality completion.