Panel calls for quicker green light on coal mining projects

Agency Feeds
N
News18•10-12-2025, 20:00
Panel calls for quicker green light on coal mining projects
- •A parliamentary panel urged faster green clearances for coal mining projects in both public and private sectors.
- •The panel highlighted significant differences in the average time taken for environmental and forest clearances between public and private projects.
- •Environmental clearance averages 15-18 months for CPSUs and 26 months for private projects; forest clearance averages 24-30 months for CPSUs and up to 34 months for private.
- •The committee sought reasons for these time discrepancies and emphasized the statutory nature of EC and FC for coal mining.
- •It recommended exploring a coordination system among stakeholders to expedite the clearance process.
Why It Matters: Expediting green clearances impacts energy projects and environmental oversight.
✦