The notice, issued on Wednesday, pertains to a 35-km stretch where construction has barely progressed, with physical and financial achievements stuck at around 4.9 per cent and 4.6 per cent of the stipulated targets
city
M
Moneycontrol25-12-2025, 14:53

NHAI Flags Contractor's 'Non-Performance' on Delhi-Mumbai Expressway, Termination Looms

  • NHAI issued an "intention to termination notice" to Roadways Solutions India Infra Ltd (RSIL) for delays on the Delhi–Mumbai Expressway.
  • The notice targets a 35-km stretch in Gujarat with only 4.9% physical and 4.6% financial progress.
  • This significant delay could push the expressway's revised completion timeline beyond March 2028.
  • RSIL, a Pune-based firm, is responsible for three stretches totaling 87 km in Gujarat, with inconsistent progress across all.
  • NHAI cited "absolute and continued non-performance" despite repeated extensions and three settlement agreements.

Why It Matters: NHAI moves to terminate contract with RSIL over severe delays on Delhi-Mumbai Expressway.