News18•27-01-2026, 15:15
CM Fadnavis Orders Superfast Completion of Mumbai's Biggest Metro Project in 1095 Days
- •CM Devendra Fadnavis has ordered the Metro Line 8 project, connecting Mumbai's two airports, to be completed in 1095 days (three years).
- •Metro Line 8 will link Chhatrapati Shivaji Maharaj International Airport to Navi Mumbai International Airport, covering 35 km with 20 stations.
- •Fadnavis emphasized obtaining all necessary permissions before project commencement and completing land acquisition within six months.
- •The project's estimated cost is 22,862 crore rupees, with 388 crore allocated for land acquisition.
- •Other approved projects include the Nashik City Parikrama Marg (66.15 km, 3,954 crore) and a four-lane cement highway in Gadchiroli for mineral transport.
Why It Matters: CM Fadnavis fast-tracks Mumbai's crucial Metro Line 8 and other infrastructure projects for rapid completion.
✦